Saturday, April 30, 2011

IT Guys

The IT crew (Rich Erickson, Craig Hillegas, Tim Olson, Lee Dodge, and Kerry Glewwe) put in some time on Saturday to run all the wiring necessary for the new computer system in the addition.


This is just a fraction of the wires and cables that are running through the ceiling of the addition.

Craig, Tim, and Lee feed cables through the ceiling. There are going to be a few guys with sore necks and shoulders tomorrow.

Friday, April 29, 2011

The Youth Room is a Pit

Crews had to dig a hole through the floor of the Youth Room to connect to the new water service that will feed the sprinkler system. The pipes go through the Youth Room, out of the church, and down the hill to Gorman Ave.




Doors, Painting, and Other Stuff

All of the doors have been hung in the new addition, although they are still missing doorknobs and windows.

Lots of Riverview volunteers put in some work this week to get the whole addition completely painted. Good work, people. This is the future home of the Youth Directors' office.

The new entryway and exterior of the main office in the new addition.

A view of the Fellowship Hall from the stairway of the new addition. The elevator and second level of the addition will be accessible through this doorway.

Saturday, April 23, 2011

Bathroom Tile

Todd and Alissa Bak, along with Matt Glewwe and Rich and Kyle Factor volunteer their Saturday morning to put down tile in the two bathrooms on the second floor of the addition.

Friday, April 22, 2011

Third Coat

Much of the addition is receiving its third coat of paint today. Here Rick Hillegas climbs a ladder on top of a scaffold to reach above the new south entry.

Bill Heinemann touches up some spots next to the windows on the second floor.

Rich Factor paints along the door frames on the first floor.

Monday, April 18, 2011

Elevator

A look down the elevator shaft from the second level.

The controls for the elevator have been installed.

Ray Glewwe takes a short ride down the elevator.

Painting and Waterproofing

Tim and Erik Olson apply another coat of paint to the walls around the new lift.


Darren Glewwe spreads some waterproofing compound on the exposed cement blocks that will soon be covered over with dirt.

Tuesday, April 5, 2011

Day 92

The Kerns, along with Mike Protelsch, begin sheetrocking the first level of the new addition.



One of the workers straddles two ladders in order to reach his work.

Saturday, April 2, 2011

Saturday

Rich Erickson starts working on the IT portion of the building project: installing a new server, computers, and security cameras.

Joy Lang and Jim Martin Paint the walls around the new lift.


Bud Hildebrandt stretches out to measure for ceiling tiles.

Ray Glewwe inspects the ceiling tiles in the Overflow Room.

Workers don their stilts in order to mud and tape the sheetrock in the new link.