Crews had to dig a hole through the floor of the Youth Room to connect to the new water service that will feed the sprinkler system. The pipes go through the Youth Room, out of the church, and down the hill to Gorman Ave.
Showing posts with label Plumbing. Show all posts
Showing posts with label Plumbing. Show all posts
Friday, April 29, 2011
Monday, February 21, 2011
Sprinklers
The weekend brought 12 inches of new snow with it, so not much work was taking place outside on Monday morning.
The sprinkler crew continued to install the new sprinkler system on Monday morning. Here a worker is drilling a big hole through a wall in one of the nursery rooms. Pipes will run down the nursery hallway and sprinklers will be installed on the walls of each nursery and preschool room.
The pipes and equipment for the sprinkler system that will be installed in the sanctuary.
Workers install pipe for the sprinkler system at the very top of the sanctuary ceiling.
Some pews had to be removed so the lift could be properly positioned.
The black pipe running diagonally through the picture is the main pipe that will feed the sprinkler system in the sanctuary.
The sprinkler crew continued to install the new sprinkler system on Monday morning. Here a worker is drilling a big hole through a wall in one of the nursery rooms. Pipes will run down the nursery hallway and sprinklers will be installed on the walls of each nursery and preschool room.
The pipes and equipment for the sprinkler system that will be installed in the sanctuary.
Workers install pipe for the sprinkler system at the very top of the sanctuary ceiling.
Some pews had to be removed so the lift could be properly positioned.
The black pipe running diagonally through the picture is the main pipe that will feed the sprinkler system in the sanctuary.
Friday, February 4, 2011
Day 50
Today marks the 50th day of construction on the Century 2.2 Project, and things are coming along well. Here you can see the progress on the second story of the new addition.
Another view of the upper level.
This is where workers cut into the floor in the nursery wing hallway in order to access sewer lines.
Another view of the upper level.
This is where workers cut into the floor in the nursery wing hallway in order to access sewer lines.
Wednesday, February 2, 2011
Days 47-48
Some of the plumbing getting laid in the addition.
Removing bricks from the exterior of the building and making space for steel beams.
Removing bricks from the exterior of the building and making space for steel beams.
Subscribe to:
Posts (Atom)


