Showing posts with label Sprinkler. Show all posts
Showing posts with label Sprinkler. Show all posts

Wednesday, May 4, 2011

More Digging

More digging had to be done to continue to connect the church's new water service for the sprinkler system. Pipes will be laid in these ditches and connected to the water supply in the street.


Friday, April 29, 2011

The Youth Room is a Pit

Crews had to dig a hole through the floor of the Youth Room to connect to the new water service that will feed the sprinkler system. The pipes go through the Youth Room, out of the church, and down the hill to Gorman Ave.




Tuesday, March 15, 2011

Painting

Larry Vidger, Chris Patrick, and Rich Factor go to work painting sprinkler pipes in the Fellowship Hall.


Friday, March 4, 2011

Progress...

The sprinkler system that was installed in the sanctuary has been painted. While the pipes are still visible, they now blend in nicely with the woodwork.

The ceiling of the second floor of the addition has been completely sheetrocked.

The location of the elevator on the second level.

Monday, February 28, 2011

Framing, Painting, and Sheetrock

Mike Johnson's crew continues to frame the new entryway.


Meanwhile, inside, the painter covered the pews with plastic to get ready to paint the newly installed sprinkler pipes.

While all that was taking place, Kerry and Korey Kern were prepping the ceiling of the second level of the addition for sheetrock.

Friday, February 25, 2011

Day 65

The Overflow Room will unfortunately be unusable for Sunday Service this week. The room is currently filled with pipes and tools for the new sprinkler system.

A view of the interior of the new link.

The same view, except taken from the other end of the link, through the missing wall of the pastor's office.

Mike Johnson's crew has begun framing the new main entryway.

Ray Glewwe removes one of the coat racks from the narthex.

Monday, February 21, 2011

Sprinklers

The weekend brought 12 inches of new snow with it, so not much work was taking place outside on Monday morning.

The sprinkler crew continued to install the new sprinkler system on Monday morning. Here a worker is drilling a big hole through a wall in one of the nursery rooms. Pipes will run down the nursery hallway and sprinklers will be installed on the walls of each nursery and preschool room.

The pipes and equipment for the sprinkler system that will be installed in the sanctuary.

Workers install pipe for the sprinkler system at the very top of the sanctuary ceiling.



Some pews had to be removed so the lift could be properly positioned.

The black pipe running diagonally through the picture is the main pipe that will feed the sprinkler system in the sanctuary.