Friday, June 3, 2011

Lots More Carpet

Bill Heinemann spreads glue while Owen Glewwe looks on.

Norm and Matt Glewwe lay the carpet tiles after the glue has been spread.

The newly carpeted Narthex.

After the Narthex is completed, Matt and Bill move on to the Nursery Wing. Matt spreads glue while Bill cuts the intricate edge pieces.

Bill and Owen discuss the complexities of laying carpet tiles.

Saturday, April 30, 2011

IT Guys

The IT crew (Rich Erickson, Craig Hillegas, Tim Olson, Lee Dodge, and Kerry Glewwe) put in some time on Saturday to run all the wiring necessary for the new computer system in the addition.


This is just a fraction of the wires and cables that are running through the ceiling of the addition.

Craig, Tim, and Lee feed cables through the ceiling. There are going to be a few guys with sore necks and shoulders tomorrow.

Friday, April 29, 2011

Doors, Painting, and Other Stuff

All of the doors have been hung in the new addition, although they are still missing doorknobs and windows.

Lots of Riverview volunteers put in some work this week to get the whole addition completely painted. Good work, people. This is the future home of the Youth Directors' office.

The new entryway and exterior of the main office in the new addition.

A view of the Fellowship Hall from the stairway of the new addition. The elevator and second level of the addition will be accessible through this doorway.

Saturday, April 23, 2011

Bathroom Tile

Todd and Alissa Bak, along with Matt Glewwe and Rich and Kyle Factor volunteer their Saturday morning to put down tile in the two bathrooms on the second floor of the addition.

Monday, April 18, 2011

Painting and Waterproofing

Tim and Erik Olson apply another coat of paint to the walls around the new lift.


Darren Glewwe spreads some waterproofing compound on the exposed cement blocks that will soon be covered over with dirt.

Saturday, March 19, 2011

Riverview Men and Women Get To Work

Joy Lang staples poly membrane to the studs. The membrane will protect the sheetrock from moisture.

Tim Olson and Kerry Kern joke around as Kerry applies an adhesive for the membrane.

Tim staples the membrane to the studs.

Matt Conway cuts the membrane into appropriately sized sheets to fit the walls in the small rooms on the first level of the addition.

Mike Johnson applies adhesive to the base of the walls on the second level in preparation for the membrane.

Work moves up to the second level, and Tim Olson and Matt Conway have at it.

Friday, March 18, 2011

Getting Our Hands dirty

Riverview guys volunteer some time to insulate the second level of the addition.